Release Planning

The purpose of this page is to provide insight into how the Release Planning XP planning practice applies to our situation. According to the Agile Book, a good starting point is to apply adaptive planning, where planning is done in increasing amounts of detail for shorter time horizons.
  • Define vision for the entire project.

  • Define the release date for the next two releases.

  • Define the minimum marketable features for the current release and start to place features that won't fit in this release into the next release.

  • Define all of the stories for the current feature and most of the current release. Place stories that don't fit into the next release.

  • Estimate and prioritize stories for the current iteration and the following three iterations.

  • Determine detailed requirements and customer tests for the stories in the current iteration.